NEYIContract furniture
The questions behind the worry

The permits: the sequence that gets you open on the date you promised

Permits are not paperwork. They are a queue, and the queue has an order. Apply for the right thing in the wrong order and you lose weeks that no amount of money buys back.

Rules differ by city, state and country. What does not differ is the shape of the sequence: the plan, then the build, then the inspection, then the licence. Everything below is written around that spine.

Why the plan review comes first

Nearly every jurisdiction wants to see your layout before you build it, because moving a sink afterwards is cheaper for them than closing you later. The review comments are also the cheapest design advice you will ever receive.

Submit early, submit complete, and expect at least one round of comments. A plan that comes back with six corrections is normal. A plan that comes back in three weeks with none usually means somebody did not read it.

The four licences almost every restaurant needs

Names change, the four categories do not: permission to operate a food business, permission to serve alcohol, permission to put tables or a sign outside, and permission to play music. Each has its own clock, and the alcohol one is usually the slowest.

What the inspector actually looks for

The first inspection is not a trap. It is a test of whether the room can be kept clean and whether the people in it know the cold chain. Inspectors look for hand basins that are reachable, cold storage that holds temperature, a documented cleaning routine, and staff who can answer a question about reheating.

The cheapest preparation is a walk-through with your own thermometer and a clipboard, two days before, pretending you are the inspector. Fix what you find and write down that you fixed it.

StageWhat gates itWhat owners lose time on
Plan reviewScaled drawings with drainage and finishesResubmitting because the duct route is missing
BuildPermits issued for the worksStarting before consent, then paying to undo
Pre-opening inspectionEquipment installed and runningCold rooms not at temperature on the day
Licence issueInspection passed, fees paidAlcohol notice period started too late

The classic waste is doing the build first because the contractor was available. Every week you save on the schedule you risk losing three on the resubmission, and the alterations you have already paid for may be the ones the reviewer removes.

Answers in this section

Publishing now. The first answers publish from 2026-12-02. This section is being filled in order, one topic at a time, so that every page you land on is already complete.

Questions that come up on this page

Can I open while a licence is pending?

Sometimes for food, almost never for alcohol. Ask the authority in writing and get the answer before you print opening dates on anything.

Do I need a separate permit for a grease trap?

Usually yes, and often from a different department than the health authority. It is one of the most common reasons a kitchen cannot be commissioned on time.

How early should I start the alcohol application?

Earlier than feels reasonable. Notice periods, background checks and committee dates can add months, and none of them speed up because your contractor finished early.